Incorrect Work value when writing to XML

Hi

I have a simple one task plan that I am trying to write to XML. The task has a duration of 1 day, one resource assigned at 10% making the work for the task 0.8 hrs or 48 mins.

When I load up an Aspose.Tasks.Project object and then stream the object to XML the resource assignment is written as 1hr and 48 mins. I cannot understad why this happens. If I make the work for the task - 30 mins then the XML file is written correctly.

I have attached a set of images that show the attributes of the project object along with the resulting XML file. Am I loading up the project object incorrectly? Please let me know if I am missing some crucial attribute.

TIA

Craig

Hi Craig,


Thank you for finding. It is our bug as I have made an incorrect rounding while writing the work values in xml.


The issue '€˜Incorrect work value when writing to xml.' with id = 14443 has been created and associated with the thread.


I have created the bug hot fix, see it attached. Sorry for inconvenience.

The issues you have found earlier (filed as 14443) have been fixed in this update.