Error when updating MS Project file

I'm facing a problem when updating a MPP file.

All Tasks are being set as collapsible (like sumary tasks), even if a task don't have children, and the ExtendedAttributes are being set to 'dropdown column' and fixed values (see attached image).

That's a sequence to simulate the problem:

1- Create a empty file.
2- Create some tasks with Aspose.Tasks.
3- Open file with MS Project, change some data and save file.
4- Open the file with Aspose.Tasks and save .

The attached source can simulate this.

Thank you for attention.
Hi Lucas,

Thank you for writing to Aspose support team.

We have investigated this issue using the latest version of Aspose.Tasks for .NET 8.2.0 and were able to replicate the same at our end. It has been logged in our bug tracking system as TASKS-33963 and TASKS-33964 for further investigation and rectification by our product team. We shall notify you here once there is some information available about this issue.

Hi José,


Both the issues were investigated and have been fixed. The upcoming version of Aspose.Tasks for .NET 8.3.0 will include the fix for both these issues. We shall notify you here once the fix version is available for download.

Hi José,

The fix version of Aspose.Tasks for .NET 8.3.0 will be available for download by today. We’ll notify you here once it is available for download.

The issues you have found earlier (filed as TASKS-33963;TASKS-33964) have been fixed in this update.


This message was posted using Notification2Forum from Downloads module by Aspose Notifier.

The issues you have found earlier (filed as ) have been fixed in this Aspose.Words for JasperReports 18.3 update.