Failure to load child tasks

When trying to load certain projects I seem to have an issue where no child items are getting loaded, and only the final milestone activity is set as the root node.

I have attached a zipped up project file which fails to load correctly, it only has the root node and no children included. There should be a couple of thousand tasks in total in the file, but these do not appear to load.

Hi Graham,


Thank you for contacting Aspose support team.

We have tested this XML file by opening it in MSP 2010/2013 but it does not display any task or resources. It seems that this file format is different than the standard project file. I am afraid that Aspose.Tasks may not read this file. Please send us an XML file which can be opened in MSP 2010. We will test the issue again and share our feedback.

Forgot to mention, this is a primavera XML file.


We have done some further investigation, and it would appear that only the items under the first WBS item are loaded.

Hi Graham,


Thank you providing more information. This issue is reproduced here and logged under Id:TASKSNET-1559 for further investigation by the product team. You will be automatically notified once any update is received in this regard.

The issues you have found earlier (filed as TASKSNET-1559) have been fixed in this update.


This message was posted using Notification2Forum from Downloads module by Aspose Notifier.