Hi there. I am having a rounding problem with durations and work.
For example, I have a task and I set the duration and work to .25, with one resource at 100%. When I open the project document, the work and duration are rounded up to .30. I can go into Project and manually change them to .25.
Is there a way I can solve this?
Hi,
Are you sure Aspose.Project rounds duration and work values?
May be MS Project rounds it?
Aspose.Project is rounding the number. I ran the code and checked the MPX file and confirmed it. It is rounding .25 to .30.
If there is any way you could fix this, I would be extremely grateful. My customers are putting in support requests asking why their project plans are off.
Cheers.