Set project calendar default working times


#1

Hi,

How can I set the default working time of any working day in my project calendar ?

I want it to start from 00:00:00:000 to 23:59:59:999, instead of the default 08:00 - 12:00 and 13:00 - 17:00.

Thank you for your help.


#2

@Opus_Team,

Thanks for contacting us. Can you please visit this link. This will help you to achieve your requirements. Please share feedback with us if there is still an issue.


#3

Thank you for the link, I already tried to set WorkingTime of working days but doing so make the duration of every task 3 times greater (as a working day is still considered 8h of work per day in the calendar). How can I set the calendar to assign a duration of 1 day for any task starting from 00:00 to 00:00 the next day ?


#4

@Opus_Team,

Can you please share source project file along with sample code so that we may further investigate to help you out.