Hi,
I’m evaluating aspose tasks for a project and I’d like to confirm some features.
First, would it be possible to update a task start date based on theirs predecessors actual start date automatically? As MSProject does?
For example:
before
task1 : start 24/02/2010; finish: 24/02/2010 – actual start : empty; actual finish : empty
task2 : start 25/02/2010; finish: 25/02/2010
where task1 is a task2 predecessor
after
setting task1 actual dates
task1 : start 25/02/2010; finish: 26/02/2010 – actual start : 25/02/2010;
actual finish : 26/02/2010
task2 : start 01/03/2010; finish: 01/03/2010
Second, would it be possible to know all the updates generated by a task property change, as in the example before, by a callback or function?
Tanks
Vítor Batista
Hi Vitor,
Hi Sergey,
I'm pleased to hear about 'Implement project data recalculate methods'.
As a suggestion only, it would be nice to see some thoughts on an incremental approach to this area rather than a long development time ... for example...
- Critical Path Recalculation based upon start and end dates and dependencies
- As above plus ... task recalc using calendars
- as above plus ... task recalc using resource calendars
- as above plus ... task recalc with resource availability and levelling
- possible other combinations..
The above is just some thoughts ... The advantage is that I can get value from some basic support and help confirm that the calculations are working and stable. (plus we don't wait until Q4'2010.)
Here are my thoughts on the overall priority of this ... my overall needs:
- Stable MS Project XML Read / Write (all versions) (100% confidence)
- Stable MS Project MPP Read (All versions) (100% confidence)
- Interface to Project Server ... on my wish list
- Stable MS Project MPP Write (All versions) ... on my wish list.
- Primavera XML Read / Write ... on my wish list
- Recalculate using Incremental approach
- Visual representation of Gantt charts etc... (I use charting packages or MS Project Viewers).
Please note ... my priorities do vary ... however, 1 and 2 are 'Must Have'; 3, 4, 5 and 6 are 'Should Have' and in fact the order can vary.
I'm sure that my needs are different from others - however, I'd be interested to see how others see the priorities.
Regards, Bruce
Hi Bruce,
The issues you have found earlier (filed as TASKS-15459) have been fixed in this update.
This message was posted using Notification2Forum from Downloads module by aspose.notifier.
(3)
The issues you have found earlier (filed as ) have been fixed in this Aspose.Words for JasperReports 18.3 update.