Perhaps I am doing something wrong, but I’ve noticed that items I deleted from my project file are showing up when I read the project file in using the Tasks.dll.
Any ideas why this would occur?
Thanks, Steve
Hi Steve,
Could you please provide us with the file as I can not see the issue in common case? You can remove or change all valued project information but keep the problem task.
Sorry for your inconvenience.
This is not a problem - found it was something else.
Hi Steve,
Thank you a lot for your answer!
We’ll add some tests just for any case. Actually MS Project MPP files contain some stubs of deleted tasks. It prevents from creating a new task with the same UID as deleted for example. Aspose.Tasks has to ignore the information now.