The bar styles of summary task don’t work as expected in the gantt chart view unless I clear the fields and reset them manually, but the behaviors of sub tasks are normal, how can I fix it?
Thank you for contacting Aspose support team again.
This issue is observed and logged under Id:TASKSNET-2097 for further investigation by the product team. You will be automatically notified once any update is received in this regard.
Although we’re using the 19.4 version of Aspose.Tasks, we’re facing the same issue when it comes to Summary Tasks or milestones : we’re applying colors to the task bars, whether they are plain tasks, summary tasks, or milestones, but unfortunately, the custom bar styles only apply to plain tasks, the other bars are simply ignored.