Hi,
How can I set the default working time of any working day in my project calendar ?
I want it to start from 00:00:00:000 to 23:59:59:999, instead of the default 08:00 - 12:00 and 13:00 - 17:00.
Thank you for your help.
Hi,
How can I set the default working time of any working day in my project calendar ?
I want it to start from 00:00:00:000 to 23:59:59:999, instead of the default 08:00 - 12:00 and 13:00 - 17:00.
Thank you for your help.
Thanks for contacting us. Can you please visit this link. This will help you to achieve your requirements. Please share feedback with us if there is still an issue.
Thank you for the link, I already tried to set WorkingTime of working days but doing so make the duration of every task 3 times greater (as a working day is still considered 8h of work per day in the calendar). How can I set the calendar to assign a duration of 1 day for any task starting from 00:00 to 00:00 the next day ?
Can you please share source project file along with sample code so that we may further investigate to help you out.