Hi,


In one of our products, I need to export bookings for resources.. For example resource 1 can booked to project 1 on March 1 for 5 hours, March 2 for 4 hours and March 3 for 6 hours. I currently am not able to find a way to do this using Aspose.Tasks.
In MSP this is the Resource Usage view. I want to manipulate the resource usage view but I am currently not able to locate how to do so. This is an important requirement for us.
Thanks

This message was posted using Email2Forum by babar.raza.

Hi Michael,

Unfortunately, your post was missed and we are extremely sorry for the delay.

You need to add a new resource assignment for each task and then add timephased data for each resource assignment to manipulate resource usage view and add your required bookings. Please have a look at http://www.aspose.com/docs/display/tasksnet/Saving+Updated+Resource+Assignment+to+MPP+file for more details on how to do that and feel free to contact us in case you have further comments or questions.