Resource Calendars

Hi, it seems that resource-calendar created with the method Aspose.Tasks.Calendar Add ( String name, Calendar baseCalendar ) are not added to the calendar-collection of the project, and so they are not written to the file. The calendar of newly created resources also does not appear in the saved file.

Thanks for help, Christian.

Hi Christian,


Thank you for posting your query.

We have investigated this issue at our end and found the same behavior as you have shared. Calendar item based on a Base calendar entry is not added to the calendars collection. We have logged this issue as TASKS-33990 in our bug tracking system for our product team to look into it. Once there is some information or fix version available for this issue, we shall write back here.

I would also request you to please share your code sample for adding resource where the resource calendar is not retained. We shall further investigate this issue and share our feedback with you.

The issues you have found earlier (filed as TASKS-33990) have been fixed in this update.


This message was posted using Notification2Forum from Downloads module by Aspose Notifier.

The issues you have found earlier (filed as ) have been fixed in this Aspose.Words for JasperReports 18.3 update.