As an input for exporting into .mpp file I have got Start date and Finish date . I need to transfer those dates info .mpp file without changes.
From the ticket mentioned above Mr. Kashif Iqbal says: “The recommended method to set task parameters is to use task start date and duration. It will make no change in the constraint type and date as well.”
I followed the ticket until the end, but unfortunately with no positive results.
I have observed your requirements and like to share that by default Saturday and Sunday are considered as off days owing to weekend. If you want them to be working days, you need to modify the calendar and set the days to be working. I request you to please visit following thread for your kind reference.
I have observed your requirements and like to share that you may need to set Saturday or Sunday as working days in your calendar to avoid issue. Please visit this documentation link for your kind reference.
does the magic for me.
For me this thread is solved.
Note: Your documentation link was useful and I really thank you for it. But… Even thou this was probably beginner question. Giving me straight answer + documentation link would make journey less painful.