Hi Aspose team!
I’m using Aspose.Task 3.6 for importing files from MSP.
I’ve 2 files (1 is mpp and another is xml which are the same data) but i do not know why the start date and finish date are different from them when reading in Aspose.Tasks.
Task “Constraint - AsLateAsPossible(1)”
- For mpp file: start date = 10/27/2010
finish date = 10/28/2010
- For xml file: start date = 11/19/2010
finish date = 11/22/2010
The start date = 11/19/2010 and finish date = 11/22/2010 when it was viewed by MSP.
Could you please take a glance at it?
I’m looking forward to hearing your feedback soon.
Thank you so much!
Ngoc
Hi Ngoc,
This issue has been logged into our issue tracking system as TASKS-31849. We will keep you updated on this issue in this thread.
As a workaround, I opened XML file in MSP 2007 and saved it as MPP and then read both the files with Aspose.Tasks for .NET and the dates were correct. We are sorry for the inconvenience.
Please feel free to contact us in case you have further comments or questions.
Best Regards,
Thank you so much for the reply.
Please let me know when it’s completed
Regards,
Ngoc
Hi Ngoc,
Sure, we will let you know once it is completed.
Best Regards,
The issues you have found earlier (filed as TASKS-31849) have been fixed in this update.
This message was posted using Notification2Forum from Downloads module by aspose.notifier.
The issues you have found earlier (filed as ) have been fixed in this Aspose.Words for JasperReports 18.3 update.